SANITARY SEWERAGE DESIGN
SANITATION
DISTRICT NO. 1 - WILDER 20-INCH COLLECTOR SEWER RELOCATION
In
the fall of 2001, Thelen Associates, Inc. documented a large
landslide between a building located at the end Beacon Drive and
the Licking River in Wilder, Kentucky. In the spring of 2002, the
Sanitation District No. 1 began experiencing damage to a portion
of their 20-inch trunk sewer that extends from the north of
University Boulevard northwardly to just west of Banklick Road
approximately parallel to the Licking River. The District then
commissioned Cardinal to perform an as-built survey of the 20-inch
sewer along the riverbank so that the extent of the damage could
be determined. The field survey determined that the landslide had
damaged the sewer main between manholes 25 and 29. Specifically,
the main between these two manholes had reverse flow or negative
gradients. The District then commissioned Thelen to prepare a
subsurface report of the landslide area with remediation
recommendations. After considering a few alternatives, Thelen
ultimately recommended an aerial truck sewer to replace the
damaged in-ground sewer. Their opinion was that with an aerial
pipe, the ground movement would not affect would not put direct
stress on the pipeline, thereby minimizing damage. Thelen
mentioned that the movement of the landslide would tend to alter
the horizontal and vertical alignment. Typically small
adjustments can be absorbed through rotation at the pipe joint.
However, in this case, Thelen recommended that we develop an
apparatus to support the pipe that was vertically
adjustable (approximately 3 inches)
throughout and horizontally adjustable at the approximate ends of
the landslide.
Based upon Thelen's Geotechnical report and
recommendations for the project, Cardinal with the assistance of a
Structural Engineer developed a unique vertically and horizontally
adjustable pipe support for installation on top of concrete aerial
piers. The support was designed to be able to withstand the
vertical and horizontal loads that could impact the pipeline.
The project was successfully completed in August 2003.
WALTON
201 STUDY/WASTEWATER FACILITIES PLAN UPDATE
For the past 18 years, Cardinal
Engineering Corporation has been the City Engineer for Walton and
has worked on countless wastewater, storm drainage, water
distribution, and roadway projects. One of the most significant
City concerns has been the wastewater system. In accordance with
Kentucky Division of Water directives in 1993, the City had
Cardinal perform an evaluation of the existing sewer system by
visually inspecting each manhole and smoke testing the lines to
see if there were infiltration (I/I) problems. Several areas of
concern were noted and repaired by the City. Later that same year
and as a follow-up to the aforementioned sewer system inspection,
Cardinal prepared a 20-year comprehensive sanitary sewer analysis
plan. The report contained recommendations for the existing
225,000 gallon per day (GPD) treatment plant including
effectiveness, size, operation, and the ability to meet future
needs.
In 1995,
Cardinal prepared a wastewater facilities plan that was submitted
to the Kentucky Division of Water to satisfy a twofold need of the
City. At that time, the City needed a plan that described the
current and future sanitary sewer system conditions and needs in
the City. Also, the City had entered into an Agreed Order with
the State regarding the condition of the City’s sanitary sewer
system. In 1996 a second treatment tank and a new sludge holding
tank was added. The existing tank was taken off line, refurbished
to what the Sanitation District No. 1 termed a “20-Year Useful
Life”, and then returned to service. The approved second tank
expansion increased capacity from 225,000 GPD to a capacity of
450,000 GPD.
Currently, Cardinal is preparing an update to the
1995 wastewater facilities plan. The updated report will be used
by the City of Walton as a planning tool for the future. In the
report, Cardinal will investigate the growth projected for Walton
until the year 2020 and also the current condition and capacities
of the sanitary sewer system within the City. The information for
this study will be obtained from discussions, meetings, and
reviews of the area with developers, public and private sanitation
owners, public officials, residents and land owners, the Kentucky
State Highway Department, contractors, planning organizations,
investigation of the existing facilities, previous sewer
investigations, road systems, land topography, the 2000 US Census,
and the Draft January 2001 printing of the 2000 Boone County
Comprehensive plan.