WATER
DISTRIBUTION PROJECTS
SUB DISTRICT D WATER MAIN
PROJECT
Cardinal
designed this water main extension in 1998 to serve portions of
Unincorporated Campbell County and Cold Spring. A Commonwealth of
Kentucky Community Development Block Grant, County/State grants,
Customer surcharges, private support, and Water District bonds
funded the project. Due to elevation pressure constraints and the
fact that some of the roadways were state maintained, the project
predominately consisted of eight (8) inch ductile iron pipe with
high-pressure fire hydrants. In a few areas, C-900 PVC was able
to be utilized. The project included 9.5 miles of water main
(33,173 feet of 8" ductile iron pipe and 15,944 feet of 8 inch
C-900 PVC) including multiple road and creek crossings. The
project consisted of complete design specifications, construction
drawings, and record drawings.
In 2002,
Cardinal designed Phase V of this project. The project consisted
of twelve (12) and eight (8) inch ductile iron pipe with
high-pressure fire hydrants. The project included 1.7 miles of
water main (7,882 feet of 12" ductile iron pipe and 1,023 feet of
8 inch ductile iron pipe) including multiple road and creek
crossings. The project is currently under construction and nearly
complete.
RYLAND HEIGHTS WATER MAIN PROJECT
Cardinal
designed this water main extension in 1995 to serve portions of
Ryland Heights, Fairview, and Unincorporated Kenton County and the
Ryland Lakes County Club. A Commonwealth of Kentucky Community
Development Block Grant, the Cities of Fairview and Ryland
Heights, Kenton County Water District Bonds, and tap fees funded
the project. Due to elevation pressure constraints and the fact
that some of the roadways were state maintained, the project
predominately consisted of eight- (8) inch ductile iron pipe with
high-pressure fire hydrants. In a few areas, C-900 PVC was able
to be utilized. The project included 14 miles of water main
(60,051 feet of 8-inch ductile iron pipe, 12,320 feet of 8" C-900
PVC, and 3,335 feet of 6-inch ductile iron pipe) including
multiple road and creek crossings. In a few locations, the water
main crossed the CSX Railroad, which required the use of boring
and jacking operations in order to accomplish the installation.
The project consisted of complete design specifications,
construction drawings, and record drawings. The project was
completed on time and within budget. Phase V was recently bid and
awarded in 2003. The project is currently under construction.